Joint Ops costs are “out of control”, says Reader


(Re: Aurora signs off on next phase of $26M Joint Ops Centre)

A few weeks ago at the invitation of the Town to the citizens, I attended an open house at the Works Department facility at 9 Scanlon Court where there was a presentation and information provided regarding the building of the new Joint Operations Centre.
At this event, it was clearly presented that the estimated construction budget was $19.8M and I received an information pamphlet indicating exactly that figure, plus $4M for land purchase.
If memory serves me correctly, the $19.8M figure is an increase of some $5M, up from the original estimated budget of $14.8M. And it has always been my understanding that the original cost estimate of $14.8M was a total estimate of building and land costs.
In The Auroran of March 6, I now read that this facility will now cost $26M. This amounts to a $6.2M difference, which I assume is for the land purchase.
But if the land purchase cost as indicated in their information pamphlet is $4M, what is the increase of some $2.2M for? I would appreciate a little clarification on this point as I'm sure other Aurora taxpayers might. It would appear to me that perhaps costs are out of control.

William Rogers
Aurora


(Editor's Note: In the video presentation, the balance was attributed to engineering costs to address topographical issues on the new site)
Post date: 2014-03-12 15:31:44
Post date GMT: 2014-03-12 19:31:44
Post modified date: 2014-03-12 15:31:44
Post modified date GMT: 2014-03-12 19:31:44
Powered by [ Universal Post Manager ] plugin. HTML saving format developed by gVectors Team www.gVectors.com